Bridgepoint Hospital Western Heavy Lift Planning

Western completed the critical lift planning for 16 components, which were placed on the 11th floor of the Bridgepoint Hospital Expansion in Toronto, Ontario; 54m (177ft) above grade. The planning was for a 550 ton hydraulic crane with 179 ft of boom, 161 ft of jib extension and a Mega Wing configuration. The critical lifts were designed to 99% of the crane’s chart capacity and the position in reference to the building and tower crane were reviewed for clearances.